08 November 2011 14:11 by H+H UK Limited
Miller Zero, Basingstoke
Location: Basingstoke
Developer: Miller Homes, Midlands & South region, Spinnaker House,
Lime Tree Way, Chineham, Basingstoke RG24 8GG.
Project: Miller Homes decided to take real customers, as well as its supply
chain, on a journey towards Code level 6 on the 3.65 acre site.
It has built five identical Miller Zero houses to different levels of the Code for
Sustainable Homes.
These homes, which are the same in layout to others on the site of 79 units,
have been completed to Code levels 1, 3, 4, 5 and zero-carbon 6.
Location: The Pinnacle, Chineham Lane, Chineham, Basingstoke,
Hampshire RG24 9LR.
Aircrete installing subcontractor: Minett Group, Units 1 & 2 Raymond Close,
Wollaston, Northants NN29 7RG.
Project description:
The CfSH houses are among 79 homes for
sale on this development. Miller had
planning permission for these houses based on 2006 Building Regulations; but
as an R & D project, it was decided to
construct some of these homes to various
levels of the Code for Sustainable Homes.
They wanted to know what the
development costs would be between
each of the Levels and additionally, how
much consumers would be prepared to
pay for homes created to the Code for
Sustainable Homes.
Building as cheaply as possible was not a
consideration for Miller, it was about
achieving the different Code Levels using
different types of materials and construction
methods. They also realised it would be the
first time that any house builder would test
this decision on the open market.
Having tested how the additional construction
costs compare, Miller Homes is now
researching the public appeal of homes built
to different levels. Once sold, each of the
homes will be monitored by Miller (with the
approval of the owners) to collect data on
their lifestyles. The model can then be
value-engineered towards possible future
sites nationwide.
Product used / aircrete specification:
The Code level 6 home is super-insulated
with the external walls built using H+H’s
200mm Vertical Elements. The Elements
themselves have excellent thermal insulation
properties = 0.11 W/mK with a compressive
strength of 3.0 N/mm2. The Vertical
Elements in combination with 200mm
Webbertherm insulation and render achieved
a U-value as low as 0.09 W/m2K.
Excellent levels of airtightness were also
achieved to help meet the mandatory heat
loss parameter required for Code 6 Homes
of 0.8 W/m2K. This is aided by the fact that
the Vertical Elements’ larger panel surface
areas of aircrete mean fewer joints, higher
levels of air-tightness and of course,
improved speed of build.
The Vertical Elements are lifted into place
using a “cast in” lifting eye at the head of
each 2.4m-high Element, which enabled the
Contractor Minett Group to build the house in
only one and a half weeks. The Elements were
installed very specifically by using a layout
drawing prepared and supplied by H+H UK,
which clearly identified where each element
should be placed.
H+H also supplied drawn details and
information specifically concerning
significantly reduced linear thermal bridging,
possible with the use of H+H aircrete material.
The Code level 3 and 4 houses were built
with H+H Jumbo Bloks (610 x 270, 100mm
thick) alongside the Code 6 house made from
H+H Vertical Elements. The H+H Jumbo
Bloks were supplied with H+H Celfix, thin
layer mortar and were used alongside a 90mm
blown-fibre insulation.
Although Thin-Joint is a well established
method of construction within the UK, Miller
did not traditionally use Thin-Joint on their
housing developments.
To align with their determination to create
something outside their usual development
and build methods, using Jumbo Bloks with
Celfix mortar seemed a natural development.
Using larger sized aircrete blocks and laying
them with a fast setting mortar enabled the
houses to be built in less time.
Traditionally, this would also mean a cost
saving to the project in time and materials.
“For whatever the reasons that timberframe
is so widely associated with
sustainability, we wanted to open up the
possibilities. No one thought they could
build Code level 6 in a masonry design.”
Ian Beal
Managing Director,
Miller Homes (Midlands and South)
Reason for choosing H+H aircrete products:
H+H aircrete can achieve significant results on
larger developments. A 20-unit development
of three-bed semi-detached houses built to
CfSH Level 3 using aircrete panels can be
used to achieve an external wall U-Value of
0.25W/m2K at a cost saving of £59/m2
compared to timber-framed or SIPS.
The discussions between Miller Homes and
H+H on the benefits of using Celcon Blocks
and Vertical Elements, along with the support
given during the whole R & D project, made a
strong case for the use of H+H aircrete for this
very unique development.
Miller Homes’ MD for the Midlands and
South-East, Ian Beal, was also very keen to
challenge the industry’s typical belief that
timber-frame is the only material which can
reach the higher levels of CfSH.
Miller decided to test this theory using both
masonry and timer framed products and
chose the Code Level 6 house to be
manufactured from aircrete, specifically to
challenge the ‘timber-framed only’ for ‘zero
carbon’ myth.
“Assumptions that our usual network of sub
contractors and suppliers would not be able
to support us with this project and that new
companies would have to be sought,
perhaps from Europe, proved inaccurate”
according to Miller Homes’ Production
Director Adrian Corser:
“The co-operation was already within our
own supply chain to make things work
in this new territory. This was
important, because we wanted a
plug-and-play solution to the Code.”
Adrian Corser
Production Director,
Miller Homes (Midlands & South)
Initial results:
The extra costs of all the Code level homes was
identified almost entirely from the addition of
the renewable technology required such as a
ground source heat pump and photovoltaics,
rather than the fabric of the buildings.
n The Code 3 house cost between £5,000
and £7,000 more than a house typically
specified to meet the Building
Regulations.
n The Code 4 house cost between an extra
£7,000 and £10,000.
n The Code 6 house’s cost to build however
was £50,000 more.
Miller Homes wants to work closely with
the occupiers to understand what the
impact, if any, the code-home features
“We are now canvassing customers to
evaluate why they would consider
buying the code-compliant houses.
Only our customers can tell us how
practical the technical interpretations
of the Code are to them. From this
ongoing research, maybe we’ll find that
some of the details prove to be a waste
of time, so we’ll know what to remove
for future designs. And we’ll see if the
high expense micro-renewables do what
they’re supposed to do.”
Ian Beal
Managing Director,
Miller Homes (Midlands and South)
Aircrete benefits:
n Excellent thermal insulation
n Excellent fire resistance
n Strong
n Good Thermal Mass
n Airtight
n Excellent Sound insulation
n Robust and Durable
n Lightweight
n Sustainable
n User friendly
n Design flexibility
Developed to enhance the key benefits
of our thin joint system; speed and quality
of build with reduced waste, H+H UK’s
Vertical Elements (200) offer all the
attributes of aircrete as a building
material whilst offering additional value
to the project.
These 200mm thick Vertical Elements can
be used in housing as well as commercial or
mixed tenure projects. Suitable for external
walls, specific acoustic solutions and fire
walls, the products will offer solutions to
meet the requirements of the Building
Regulations and Code for Sustainable
Homes (CfSH), for Education, Health, Care
Homes, Retail outlets, Hotels, Commercial
buildings, Leisure, Offices as, well as
Housing (social and private).
H+H Vertical Elements (200) are made
to extremely tight manufacturing
dimensional tolerances, supplied
specifically for use with a combination of
ancillary products which all complement
the 2mm joint of Celfix, our thin layer
mortar, with no levelling required, this
ensures a quality and quick build with
little or no site wastage.
H+H Vertical Elements are sold as a
package including most materials
required to build the walls, priced either
as supply and build (quoted including
labour) or supply only (quoted as a
materials only price).
Submit your news
Send us your construction related news and press releases to feature on specifinder.com free-of-charge. Email them to [email protected]
Add your company
An entry on specifinder.com gives you exposure to over 32,000 unique visitors a month. For further information, please email [email protected]
Tweets by @specifinder


